Chamala Vidhyadhar v. The State of Telangana
Case brief
What is this about?
Writ petition; electricity connection; Occupancy Certificate; Completion Certificate as condition precedent; TGSPDCL; GHMC; building permit dated 23.01.2023; abandonment of undertaking-based release practice; unauthorised floors; building regularisation scheme; Rajendra Kumar Barjatga v. U.P. Avas Evam Vikas Parishad, 2024 SCC OnLine SC 3767 (followed); Re: Directions in the matter of demolition of structures (referred); Article 226 mandamus; Section 151 CPC application; Kapra Circle-1, LB Nagar Zone, Medchal-Malkajgiri; disposed of without costs, petitioner to obtain Occupancy Certificate first.
What did the court decide?
None of the prayed reliefs; petitioner directed to first obtain the Occupancy Certificate from the municipal authorities, upon production of which TGSPDCL shall consider release of the electricity connection in accordance with law. No costs.