M/S S.P.Singla Constructions(P) v. the Chief Engineer (the Employer) World Bank Anr.
Case brief
What is this about?
In this arbitration petition, the petitioner challenged the appointment of an arbitrator nominated by the respondent's superior officer, arguing it violated the contract and statutory provisions regarding independence. The court found the appointment valid as it was initiated by the employer within departmental hierarchy rules.
What did the court decide?
The petition challenging the appointment of the arbitrator is dismissed.