What is this about?
Petitioner sought arbitrator appointment under Section 11 for a construction contract dispute. The Court found a dispute existed regarding the validity of a full and final settlement receipt alleged to be signed under pressure. A former judge was appointed to decide the dispute.
What did the court decide?
Appointment of former Judge N.K. Aggarwal as arbitrator to decide the dispute.