M/S Gawar Construction Co. v. State of Haryana & Ors.
Case brief
What is this about?
The High Court dismissed an application for appointment of an arbitrator in an arbitration case. The Court held the petitioner was estopped from raising a new dispute regarding the extension of the Defect Liability Clause because they failed to object to the Engineer's decision within the 14-day period mandated by the agreement.
What did the court decide?
Application for appointment of an arbitrator was dismissed as the petitioner was estopped from raising the dispute due to non-compliance with contractual notice periods.