Lalan Kumar v. The State of Bihar
Case brief
What is this about?
CWJC No. 346 of 2023, Patna High Court, decision date 03-09-2025, single judge A. Abhishek Reddy; incentive bonus for early completion under Clause 2A of Agreement No. 2 (SBD) 2018-2019, 1% of tendered value per month capped at 5%; Schedule F 'Yes/No' box left unticked held to be authorities' lapse, no bar to bonus; agreement binding once entered, to be implemented in letter and spirit; delayed application dated 16.05.2020 excused due to COVID-19 lock down March 2020-end 2021; writ maintainable in contractual matters, no disputed questions of fact, Article 226 jurisdiction not excluded, Article 14 arbitrariness; precedents: Bharat Petroleum Corporation v. Great Eastern Shipping (2008) 1 SCC 503 (agreement sub silentio / acceptance by conduct), Unitech v. TSIIC 2021 SCC OnLine SC 99 and ABL International v. ECGC (2004) 3 SCC 553 (writ maintainable for contractual claims against State/instrumentality), UPPTCL v. CG Power (2021) 6 SCC 15 (listed/referred); impugned Memo No. 1838 dated 16.11.2022 of Chief Engineer (South), Building Construction Department, Patna set aside; claim amount Rs. 25,15,668/-; payment directed preferably within eight weeks, default attracts simple interest 6% per annum from date of application till actual payment; prior related case CWJC No. 4654 of 2022 disposed 22.04.2022; work: D-type residential buildings G+3, Sale Tax Campus, Adampur, Bhagalpur; work order 31.12.2018, agreement 14.02.2019, completion 20.02.2020, possession handed over 29.02.2020.