Shibram @ Shibaram Majhi v. State of Odisha
Case brief
What is this about?
Section 28-A Land Acquisition Act 1894; redetermination of compensation; enhanced compensation; LAR No.183 of 2010; Lower Indra Irrigation Project; Khariar; Nuapada; Konabira; Notification No.1767 dated 09.01.2001; section 18 reference; section 4(1) notification; Department of Water Resources Odisha sanction order; Letter No.1187 dated 22.07.2025; time-bound disposal writ direction; State of Odisha.
What did the court decide?
Direction to Opposite Party No.3 to dispose of the Petitioner's application under section 28-A of the Act in accordance with law, as expeditiously as possible, preferably by end of September, 2025, and to communicate the decision to the Petitioner forthwith; if the Petitioner is found entitled to enhanced compensation in terms of the judgment in LAR No.183 of 2010, the differential amount together with other statutory dues is to be released as expeditiously as possible, preferably by end of December, 2025.