Madhab Majhi v. State of Odisha
Case brief
What is this about?
Madhab Majhi v. State of Odisha and Others, W.P.(C) No.15305 of 2025, High Court of Orissa at Cuttack, order dated 24.07.2025, coram Justice K.R. Mohapatra and Justice Savitri Ratho. Keywords: section 28-A Land Acquisition Act 1894; redetermination of compensation; Lower Indra Irrigation Project, Khariar; Nuapada; LAR No.21 of 2021; Notification No.23428 dated 16.05.2001; section 18 reference; section 4(1) notification; sanction order Department of Water Resources; Letter No.1053 dated 08.07.2025; direction to dispose section 28-A application by end of September 2025; release of differential compensation with statutory dues by end of December 2025; Dhananjaya Mund; Sibanarayan Biswal.
What did the court decide?
Writ petition disposed of with a direction to Opposite Party No.3 to dispose of the Petitioner's application under section 28-A of the Land Acquisition Act, 1894 in accordance with law, as expeditiously as possible, preferably by end of September, 2025, and communicate the decision forthwith; if the Petitioner is found entitled to enhanced compensation in terms of the judgment in LAR No.21 of 2021, the differential amount along with other statutory dues shall be released, preferably by end of December, 2025.