observation or finding. No claim has been put before us either in the pleadings or during the course of the arguments that if there is any discrepancy, Tribunal may appoint another Committee to verify the distance. In fact, a lame reliance has been placed on Distance Certificate dated 03.09.2016 without doubting the correctness of Tehsildar’s subsequent letter dated 02.05.2023 showing that siting criteria was not being matched by the project proponent. This is fortified by the own document relied by respondent 6 to 8 i.e., annexure 8 which is JKPCC inspection Report showing that within 500 meters, approximately more than 20 houses are existing and education institutions also existed at a distance of about 500 meters. This is their own document relied by respondents 6 to 8 and when this very document shows that proponents have not complied with the siting criteria, in the absence of any explanation on this aspect, we find no reason but to draw conclusion that respondents 6 to 8 units were established in violation of siting norms and therefore, cannot be allowed to continue at the site in question i.e., khasra no. 256 at village Chaktroo, Tehsil Haveli and District Poonch. Joint Committee Report therefore to this extent, deserves to be accepted.