Madras High Court, Madurai Bench; W.P.(MD)No.6293 of 2026; Murugesan v. District Collector, Dindigul and others; writ of mandamus under Article 226; land survey; Survey No.904/4D; 25 cents; Old Batlagundu Village; Nilakottai; Dindigul District; joint patta; joint pattadhars; police protection; Tahsildar; Head Surveyor; Inspector of Police, Batlagundu Police Station; Standard Operating Procedure for survey notices and signatures; 12-week completion timeline; petitioner's representation dated 11.01.2026; disposed of without costs; Justice S.Srimathy; decision date 10.03.2026.
What did the court decide?
Survey of Survey No.904/4D (25 cents), Old Batlagundu Village, to be conducted by the 2nd respondent with the 3rd respondent's assistance after notice to the petitioner and joint pattadhars; police protection by the 4th respondent if required; adherence to the Standard Operating Procedure; completion within 12 weeks from receipt of a copy of the order; no costs.