G.Balasubramaniyan v. The Managing Director
Case brief
What is this about?
Delayed payment of retirement/terminal benefits; interest at 6% per annum for belated settlement; Tamil Nadu State Transport Corporation (Kum) Limited, Kumbakonam; TNSTC Pension Fund Trust; writ of mandamus under Article 226; S.K. Dua v. State of Haryana 2008 (3) SCC 44; W.A.(MD)No.403 of 2010 batch common order dated 04.07.2014; retirement 31.07.2024; settlement 02.12.2025; representation 06.12.2025; Madurai Bench of Madras High Court; B. Pugalendhi, J.; WP(MD)No.2742 of 2026; decided 03.02.2026; petition allowed, no costs.
What did the court decide?
Interest at 6% per annum on the delayed/belated payment of the petitioner's retirement/terminal benefits, payable within six months from the date of receipt of a copy of the order; no costs. ¶39