What is this about?
Cancellation of civil works contract for delay; writ petition dismissed; no automatic extension of time; Clause 16.2 progress notice absent but no right to extension; contractor failed to adhere to contractual schedule; no arbitrariness or mala fides established; Article 226 certiorarified mandamus; National Health Mission 2025-2026; 15th Central Finance Commission Grant; Primary Health Centre Mangadu, Munchirai Panchayat Union; Health Sub-Centre Mathur; Thiruvattar Panchayat Union; Kanyakumari; District Rural Development Agency; G.Jeevaraj v. District Collector, Nagercoil; M.Dhandapani J.; Madurai Bench of Madras High Court; 14.07.2026.
What did the court decide?
It is not in dispute that the petitioner failed to complete the works within the period stipulated under the respective agreements. ¶54