TANGEDCO excess demand penalty; provisional assessment treated as show cause notice; LTCT 3-phase service connection S.C.No.0543801456; kraft paper board manufacturing unit; sanctioned demand 112 KW; maximum demand 174.22 KW recorded 16.04.2018; alarm and K.W. trip mechanism; provisional assessment Rs.17,13,747/- for 24.04.2018-29.06.2018; penalty Rs.13,83,514/-; impugned demand dated 11.07.2018 by Assistant Engineer, Keeladi; objections within two weeks; personal hearing; reasoned final assessment order within two weeks thereafter; Article 226 Certiorari; W.P(MD)No.17682 of 2018 with WMP(MD) Nos.15568-15570 of 2018 & 17677 of 2019; Madurai Bench of Madras High Court; Justice M.Dhandapani; disposed of; no costs; counsel J.Anandkumar (petitioner) and S.Deenadhayalan, Standing Counsel (respondents).
What did the court decide?
Writ petition disposed of with no costs and connected miscellaneous petitions closed; provisional assessment/demand dated 11.07.2018 treated as a show cause notice, petitioner to submit objections/explanation within two weeks, and respondents to consider the objections, afford a personal hearing, and pass a reasoned final assessment order on merits and in accordance with law within two weeks thereafter.