K.Madhesh v. the Superintending Engineer
Case brief
What is this about?
Keywords: writ of mandamus; Madras High Court; NH-844 road widening; NHAI land acquisition; TANGEDCO electricity service connection removal; blocked property access; representations dated 10.03.2025, 07.04.2025, 16.10.2025; Survey Nos. 603/2E1 and 603/2E2; Pappinaickanahalli Village, Dharmapuri; Krishnagiri; petition closed without orders and without costs. Relevant to disputes where utility infrastructure left on acquired land obstructs access and relief is secured administratively before adjudication, and to mandamus petitions rendered infructuous by executive action during pendency.
What did the court decide?
Relief realised administratively: after TANGEDCO's survey found S.No. 603/2E2 belonged to NHAI, the electricity service connection standing on the damaged wall was removed on 19.01.2026; the Court recorded this statement, held the claimed relief considered and granted, required no orders, and closed the petition without costs.