M/S.Royaltech Marine Engineers v. Assistant of Commissioner (Apfc)
Case brief
What is this about?
Single-judge Madras High Court writ petition (Article 226, Certiorari Mandamus) by M/s.Royaltech Marine Engineers (proprietor G.Pandiyaraj, Chennai) against the Assistant PF Commissioner, EPFO Regional Office, Chennai, challenging proceedings TN/RO/CHN-I/CCI(PDC)/TN/93070/Div-511/2024 dated 20.06.2024 demanding EPF & MP Act Section 7Q interest of Rs.3,70,609/- and Section 14B damages of Rs.7,41,947/- despite prior Section 7A dues of Rs.7,98,119/- being recovered. Court held 7Q interest cannot be imposed once amounts are recovered/paid; reduced 14B damages with remaining 40% payable in six instalments; default permits further recovery per law. Disposed of, no costs, connected WMP closed. Keywords: EPF & MP Act, Section 7A, 7Q interest, 14B damages, attachment, recovery, instalments, financial constraint.
What did the court decide?
Writ Petition disposed of with directions: the Section 7Q interest component cannot be imposed (and has been paid); the 14B damages are reduced, with the remaining 40% payable in six instalments, failing which the respondent/Commissioner may proceed in accordance with law for further recovery; no costs; connected Writ Miscellaneous Petition closed.