M.Bhuvaneswari v. The Superintending Engineer
Case brief
What is this about?
Electricity connection petty shop; TANGEDCO Madurai; writ of mandamus; Article 226 Constitution of India; implementation of earlier order WP(MD)No.13336 of 2025 dated 30.04.2025; alleged non-compliance by respondents; petitioner's failure to submit online application; respondents' communication dated 05.06.2025; dismissal at admission stage by consent; liberty to reapply; adherence to time schedule of earlier order; no costs; connected W.M.P(MD).No.23126 of 2025 closed; Madurai Bench of Madras High Court; P.T. Asha J.; 25.10.2025; W.P.(MD)No.29896 of 2025.
What did the court decide?
Writ petition dismissed with no costs; liberty granted to the petitioner to submit the online application as sought for in the respondents' letter dated 05.06.2025, on receipt of which the respondents shall adhere to the time schedule granted in the earlier order; connected miscellaneous petition (W.M.P(MD).No.23126 of 2025) closed.