M/s.P.Samiyappa Gounder and Bros v. The Superintending Engineer
Case brief
What is this about?
Condonation of delay; 230 days delay in representation of appeal suits; A.S.(MD)SR.Nos.27191 and 27192 of 2025; Madras High Court Madurai Bench; C.M.P.(MD)Nos.19014 and 19015 of 2025; petitioner M/s.P.Samiyappa Gounder & Bros., Kangayam, Tirupur District; respondents PWD/WRO officials (Superintending Engineer, Special Project Circle Palani; Executive Engineer, Nanganjiyar Basin Division, Palani, Dindigul District; Chief Engineer, Pollachi Region, Coimbatore); delay condoned on affidavit reasons; appeal to be numbered if in order; listing fixed 27.11.2025; decided 25.11.2025 by C.V.Karthikeyan and R.Vijayakumar, JJ.; counsel S.Venkatesh for petitioner, A.Kannan Addl. Govt. Pleader for respondents.
What did the court decide?
Delay of 230 days in representing A.S.(MD)SR.Nos.27191 and 27192 of 2025 condoned; Registry directed to number the Appeal Suit if otherwise in order; connected civil miscellaneous petitions to be listed on 27.11.2025.