M/s. Njr Constructions Pvt. Ltd., Rep.by its Managing Director Mr.N.Janardhana Rao, v. Union of India, Cpwd
Case brief
What is this about?
Section 34 Arbitration and Conciliation Act 1996; set aside award; annul award; unintelligible reasoning; patent illegality; no reasons; no finding on responsibility for delay; liquidated damages; levy; extension of time; prevention principle; time at large; time not essence of contract; justified delay 165 of 444 days; Chief Engineer decision final and binding; Competent Authority report; Clause 2 GCC compensation for delay; Clause 25; Mitra Guha Builders distinguished; Multiplex Constructions prevention principle applied; Dyna Technologies reasoned award; Gayatri Balasamy severability modify award; McDermott International annul fresh arbitration; interest enhanced 7.5% to 12%; costs of arbitration Rs.4,00,000; CPWD construction contract; NJR Constructions v Union of India CPWD; Madras High Court Commercial Division; partly allowed.
What did the court decide?
Original petition partly allowed. Award of the sole Arbitrator set aside in so far as claim Nos.2, 7 and 8 are concerned. Claim No.2: award annulled, parties left open to resort to arbitration afresh if so advised. Claim No.7: post-award interest on claim Nos.3, 5 and 6 modified to 12% per annum from the date of award till the date of actual payment, and 7.5% per annum from 08.3.2020 till the date of passing the award. Claim No.8: respondent directed to pay Rs.4,00,000/- (Rupees four lakhs only) towards costs to the petitioner.