Malliga S v. the Chief Engineer
Case brief
What is this about?
In this writ petition, the petitioner challenged the failure of TANGEDCO authorities to provide an electricity connection to her house. The court directed the petitioner to submit an online application within two weeks, upon which the respondents must consider it and grant connection within six weeks, disposing of the petition without addressing the merits of the underlying title dispute.
What did the court decide?
Directed the petitioner to file an online application for electricity connection within two weeks; directed the respondents to consider and grant the connection within six weeks if in order.