Opg Power Generation Pvt. Ltd. v. Tamil Nadu Generation and Distribution
Case brief
What is this about?
The High Court was approached by electricity generators seeking quashing of demand notices for open access charges levied during the COVID-19 lockdown. The Court held that the dispute regarding usage and charges falls within the adjudicatory jurisdiction of the Tamil Nadu Electricity Regulatory Commission (TNERC) under the Electricity Act, 2003. Consequently, the writ petitions were referred to TN
What did the court decide?
The writ petitions were disposed of by referring the issues regarding open access charges during the lockdown to the TNERC for final adjudication within four weeks, subject to continuation of the inte