Mr.M.K.Dhanraj, v. the Commissioner
Case brief
What is this about?
Petitioner challenging delay in granting construction permission for a second floor under Hindu Religious and Charitable Endowments Act. Court quashed delay and directed First Respondent to consider representation, enquire, and pass orders within eight weeks with notice to interested parties.
What did the court decide?
Directions to First Respondent to consider representation dated 28.11.2013, enquire, afford hearing opportunity, and pass orders within eight weeks.