This High Court dismissed a Civil Miscellaneous Appeal challenging an Order and Executive Order dated 18.12.2015 passed in Arbitration O.P.No.67 of 2015. While confirming the impugned order, the Court directed the respondents to return development charges and pay compensation for trees, standing crops, solatium, and interest.
What did the court decide?
The impugned order was confirmed; development charges to be refunded; compensation for trees and crops to be determined within eight weeks; solatium and interest payable.