The Project Director,National v. S.Razzia
Case brief
What is this about?
This court dismissed the civil miscellaneous appeal under the Arbitration and Conciliation Act, confirming the arbitrator's award. The court ordered the return of deducted development charges and granted additional compensation for trees and standing crops to be determined by the respondent authority.
What did the court decide?
Award confirmed; return of development charges granted; compensation for trees, crops, solatium, and interest ordered.