The Catholic Syrian Bank Ltd. v. a 2 Z Builders (P) Ltd.
Case brief
What is this about?
The appellant bank argued for full one-year commission on a bank guarantee held for only 96 days. The High Court held the bank entitled to six months' commission, allowing recovery of the excess paid and re-fixing interest rates.
What did the court decide?
Recovery of excess commission of Rs. 5,34,000/ granted; interest rate re-fixed at 9% per annum from 27.06.1996 until date of decree.