M/S.Vismaya Rocks (P) Ltd. v. the State Environment Impact Assessment Authority
Case brief
What is this about?
Environmental clearance holders sought time-bound consideration of revalidation based on project life. The court disposed of the petitions, directing applications within one week, SEIAA requests for further documents within two weeks thereafter, and decisions within four months of receiving the required information.
What did the court decide?
SEIAA directed to seek further documents within two weeks of receiving revalidation applications and decide them within four months of receiving the required information.