M.P.Kuriakose v. the State Environment Impact Assessment Authority
Case brief
What is this about?
Environmental clearance holders sought extension of earlier directions for re-validation based on project life. The court disposed of the petitions, requiring applications within one week, communication of further requirements within two weeks, and SEIAA decisions within four months of receiving the requested information.
What did the court decide?
SEIAA directed to notify further requirements within two weeks of receiving applications and decide re-validation applications within four months of receiving the requested information.