Rajesh N.D v. State of Kerala
Case brief
What is this about?
Petitioner, a government contractor, challenged non-payment for urgent renovation work executed without prior administrative sanction. Court directed Chief Engineer to issue ratification within three weeks and expedite payment of dues including GST.
What did the court decide?
Directed 2nd Respondent to issue orders on ratification within three weeks and ensure payment including GST is made expeditiously.