Musthafa, v. State of Kerala
Case brief
What is this about?
The Court directed the 8th respondent to finalize the petitioner's application for removal from the data bank within three months. It also directed the 3rd respondent to consider the petitioner's regularization application within three months if enabling orders are produced, and the Municipality to reconsider building permit applications accordingly.
What did the court decide?
Direction to 8th respondent to finalize application within three months; direction to 3rd respondent and Municipality to consider applications/orders within three months.