M/S. Reena Engineers and Contractors Pvt. Ltd. v. Kerala Water Authority
Case brief
What is this about?
In a writ petition regarding non-payment of work bills by Kerala Water Authority, the Court directed the Authority to pay the due amounts within three months, finding that paucity of funds cannot be an excuse for indefinite delay if work was completed satisfactorily.
What did the court decide?
Direct the Water Authority to disburse the amounts due to the petitioner within three months from the date of receipt of the judgment copy.