M/S.Reena Engineers and Constractors Pvt. Ltd. v. Kerala Water Authority
Case brief
What is this about?
The High Court allowed this writ petition, holding that the Kerala Water Authority could not delay payment indefinitely due to paucity of funds. The petition, which concerned delayed disbursement of amounts for satisfactorily completed work, was permitted with a direction to pay within three months.
What did the court decide?
The Kerala Water Authority is directed to disburse the amounts due to the petitioner within three months from the date of receipt of a copy of the judgment.