all necessary clearances. The petitioner decided to enhance the capacity of the project to 500 beds and Exhibit P7 application for environmental clearance was submitted for permission to construct built up area of 30618.57m2 . The application was dated 28.10.2015. The 2nd respondent, before whom the applications were submitted, forwarded the request to the 3rd respondent. It is stated that on 11.07.2016, the 3rd respondent appraised the project and required the production of documents to show that the land is exempted from the purview of the Kerala Conservation of Paddy Land and Wetland Act, 2008. Exhibit P8 is the minutes. The petitioner produced the required documents with Exhibit P9 covering letter. It is submitted that 3rd respondent conducted a site visit on 01.10.2016. By Exhibit P10 proceedings dated 16.11.2016, the 3rd respondent recommended the project, subject to the condition that waste water discharge to public drains shall be minimal and after observing strict treatment protocol. The 2nd respondent was requested to direct the petitioner to enhance the amount of Corporate Social Responsibility to Rs.15 lakhs per year. The petitioner, by Exhibit P11, confirmed willingness to abide by the conditions. However, by Exhibit P12, minutes of the meeting held on