A.R.George v. the Secretary
Case brief
What is this about?
writ petition filed by a small contractor alleging illegal withholding of final bill amount. Court directed respondents to specify remaining work within a week. Petitioner granted two weeks to complete work. Payment of final bill ordered only after satisfactory completion of remaining works.
What did the court decide?
The 1st respondent to specify remaining works in writing within one week; Petitioner to complete work within two weeks thereafter. Final bill payable upon satisfactory completion.