A.K.Varkey v. Muvattupuzha Municipality
Case brief
What is this about?
A contractor filed a writ petition seeking payment for an abandoned anganvadi construction project. The Municipality, represented by the Secretary and Chairman, failed to file a counter affidavit or appear. The Court directed the Municipality to compute and release the payment for completed work within two months, leaving the interest claim open.
What did the court decide?
Directed the municipality to compute and release the amount payable for work done within two months from receipt of this judgment.