Mohammed Shereef C. v. Secretary, Kappur Grama Panchayat
Case brief
What is this about?
Petitioner challenged an order stopping factory operations due to alleged pollution. Court noted PPCB report showed parameters within limits and directed petitioner to implement five remedial measures within one month to resume operations.
What did the court decide?
Directed petitioner to implement five remedial measures from the Third Respondent's report dated 20.11.2010 within one month and allow joint inspection for resumption.