BESCOM electricity disconnection notice; KIADB NOC demand within seven days; notice treated as show cause notice; objections within two weeks; no coercive steps or disconnection till appropriate order; writ disposed under Articles 226 and 227; follows Suresh R., W.P.No.8047/2025 and connected WPs (DD 11.03.2026); petitioner Smt. Renuka Kamasetty; Doddanekundi Phase I Industrial Area; RR No.E12TPM-2463.
What did the court decide?
Liberty to file objections to the impugned notice within two weeks; impugned notice to be treated as show cause notice, with the competent authority to consider the objections and pass appropriate orders in accordance with law; respondents restrained from taking coercive steps, including disconnection of electricity, till such consideration; all contentions kept open. ¶48