M/S Shiva Irrigation Systems v. the Managing Director
Case brief
What is this about?
BESCOM estimate revision challenged by writ of certiorari under Articles 226 and 227; underground (UG) cable; self-execution scheme; revised estimate Rs.2,44,98,684/- vs earlier engineers' estimate Rs.18,89,806/-; joint inspection and survey sketch; fresh estimate along route G–F; KPTCL and BESCOM respondents at Tumakuru/Chitradurga; small-scale PVC pipe irrigation industry at Gubbi, sanctioned load 1298 KVA under R.R. Nos. GHT-20 and GHT-27; F-25/F-16 feeders; regularisation of F-J-H cable via quality approvals/NOC; Annexure-X notice dated 20.12.2025 kept in abeyance; no coercive steps condition.
What did the court decide?
Impugned communication dated 26.09.2025 (Annexure-A) issued by respondent No.5 quashed; Respondent No.4 to issue fresh intimation/estimate for the UG cable along route G–F within two weeks; petitioner to execute the work under the self-execution scheme upon receiving the intimation; petitioner to obtain quality approvals/NOCs for the existing F-J-H cable within six months, upon which BESCOM shall regularise it; till compliance no coercive steps and the Assistant Executive Engineer's notice dated 20.12.2025 (Annexure-X) kept in abeyance for six months; on failure, respondents free to initiate appropriate action in accordance with law.