Sri Battarusetty Venkata Sunil v. State of Karnataka
Case brief
What is this about?
BESCOM electricity disconnection notice; KIADB No Objection Certificate (NOC) demand; construction alleged contrary to sanctioned plan with no KIADB determination; notice treated as show cause notice; objections within two weeks; interim restraint on coercive steps including power disconnection to RR E12TPM-3373; parity with Suresh R. (W.P.No.8047/2025, DD 11.03.2026); writ petition Articles 226 and 227; GM-KEB; Karnataka High Court; KIADB; Bangalore Electricity Supply Company.
What did the court decide?
Petitioner permitted to file objections to the impugned BESCOM notice within two weeks; notice to be treated as show cause notice with the competent authority to consider objections and pass appropriate orders in accordance with law; respondents barred from taking coercive steps, including disconnection of electricity, till such consideration and orders.