Learned counsel for the respondents/ State has submitted, that nothing wrong has been done by the respondent authority and in pursuance of the order passed by this Hon’ble Court, reasoned order has been passed by Zila Parishad, Ramgarh stating therein at page no.72 of the writ petition, that the 10% of the agreed amount of Rs.22,46,526/- can be deducted under delayed work and security deposit. The amount, which has been deducted to the tune of Rs. 1,05,062/- towards security deposit and delayed deduction Rs. 1,18,146/- comes to Rs.2,23,208/-, which is less than 10 % of the agreed amount of Rs.22,46,526/- deducted in terms of liquidated damage as provided under Clause-2 of the terms and conditions of the contract, as such, this court may not interfere with the said order passed by the Deputy Development Commissioner-cum-Chief Executive Officer, Jila Parishad, District- Ramgarh.