What is this about?
An interlocutory application by a petitioner company to withdraw a writ petition challenging contract termination and extend interim protection regarding bank guarantees. The court closed both petitions based on a consensus between parties.
What did the court decide?
Writ petition and interlocutory application closed on consensus; interim protection extended for two months subject to extension of bank guarantees.
What the court decided
Page No.# 1/10
GAHC010025762023
THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : I.A.(Civil)/311/2023
M/S GANNON DUNKERLY AND CO. LTD. 864, TOPSIA ROAD (SOUTH), HAUTE STREET , (7 TH FLOOR) KOLKATA, 700046, WEST BENGAL
REP. BY ITS AUTHORIZED SIGNATORY/ DEPUTY GENERAL MANAGER HR AND ADMIN, ASHIS KUMAR PAL
S/O- PRANBALLAV PAL OF GANNON DUNKERLY AND CO. LTD, 864, TOPSIA ROAD (SOUTH), HAUTE STREET , (7TH FLOOR) KOLKATA, 700046, WEST - BENGAL
VERSUS
THE UNION OF INDIA AND 4 ORS.
REPRESENTED BY THE SECRETARY TO THE GOVT. OF INDIA, MINISTRY OF ROAD TRANSPORT AND HIGHWAYS, GOVT. OF INDIA, 3RD FLOOR, PTI BUILDING AND PARLIAMENT STREET , NEW DELHI-110001
2:THE MANAGING DIRECTOR
Parties & counsel
- respondent
The Union of India
- respondent
National Highways And Infrastructure Development Corporation Limited
Coram
Manish Choudhury
Case details
As recorded by the court registry
- Court
- Gauhati HC
- Decided on
- · February
- Registered
- Case no.
- I.A.(Civil)/311/2023