Punjab National Bank v. M/S Protech Aqua Solution Pvt. Ltd.
Case brief
What is this about?
The Tribunal allowed the applicant bank's recovery application against the primary borrower for dues amounting to Rs. 35,61,169.37. It declined to implead the director defendants as they did not provide personal guarantees, granted interest at 10.50% p.a., and ordered an injunction on asset transfer.
What did the court decide?
Recovery of Rs. 35,61,169.37 with interest at 10.50% p.a., costs, injunction against asset transfer, and issuance of a Recovery Certificate.