This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
BEFORE THE DEBTS RECOVERY APPELLATE TRIBUNAL, AT: MUMBAI Present: Mr Justice Ashok Menon, Chairperson
I.A. No. 838/2023
In Misc. Appeal No. 66/2023
Between
Punjab and Sind Bank … Appellant/s V/s.
M/s. Patil Constructions & Infrastructure Ltd. & …Respondent/s Ors.
-: Order dated: 17/01/2024:-
Respondent No. 1 has filed a reply together with the application to receive it out of time.
Heard both sides I.A. No. 838/2023 is allowed and the reply is received subject to payment of cost ₹ 2,000/- to the DRT Bar Association for purchase of books and periopdicals, within a week.
Post on 01.02.2024 before Registrar.
Sd/Chairperson
rm-20
1
Punjab and Sind Bank
M/s. Patil Constructions & Infrastructure Ltd.
Ashok Menon
As recorded by the court registry