The appeal filed by the Bank was dismissed as infructuous because the interim order against which it was filed had merged with a finally decided interim order (T.A No. 473/2002).
What did the court decide?
Dismissed as infructuous.
What the court decided
Appeal Dy. No. 498/2023 Date: 03.05.2023
Bank of Baroda Vs. Pegasus Asset Reconstruction Pvt. Ltd.
Present: Shri Udai Karan Saxena, Sr. Advocate assisted by Shri Avinash Jaiswal, Counsel for the appellant-Bank,
Shri Sandeep Arora, counsel for the respondent-Bank,
It has been intimated by the learned counsel for the respondent-Bank that T.A No. 473/2002 has finally been decided, as the present appeal has been filed against the interim order, which has now merged with the final order, therefore, the same has become infructous, hence the same may be dismissed as infructuous. The said averment has not been objected to by the learned counsel for the appellant.
In view of the above, the present appeal is dismissed as having become infructuous.
Justice R. D. Khare Chairperson
VN Giri
Parties & counsel
- appellant
Bank of Baroda
- respondent
Pegasus Asset Reconstruction Pvt. Ltd.
Coram
Shri R.D. Khare
Case details
As recorded by the court registry
- Court
- DRAT
- Decided on
- · May
- CNR
- 091090004982023
- Topic
- Banking and Recovery
All orders in this case
2 orders share this CNR
- Order 1 · LD Registrar
- Order 2 — this page · Rajesh Dayal Khare