Asset Reconstruction Company India Ltd. v. Smt Mydam Nagarani Ors.
A compact analysis
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
IN THE DEBTS RECOVERY APPELLATE TRIBUNAL AT KOLKATA
(Appeal No. 39 of 2015)
(Arising out of S.A. 327 of 2011 in DRT, Visakhapatnam)
THE HON’BLE MR. JUSTICE ANIL KUMAR SRIVASTAVA CHAIRPERSON
20.04.2022 Asset Reconstruction Company (India) Limited … Appellant -vsSmt. Mydam Nagarani & 8 Others … Respondents Mr. Rohit Das with Ms. Kishwar Rahaman and Mr. Preetam Majumdar, Learned Counsel for Appellant Mr. Debasish Chakrabarti with Ms. Sharmistha Pal, Learned Counsel for Respondent Bank
THE APPELLATE TRIBUNAL :
The matter is taken up in the second call.
Learned Counsel for Appellant submits that an e-mail message has been received from the Appellant to the effect that the account has been settled with the Respondents. Learned Counsel prays for and is granted two weeks’ time to file proper application for withdrawal of the appeal.
List the matter on 18th May, 2022.
(Anil Kumar Srivastava,J) Chairperson
Parties & counsel
- appellant
Asset Reconstruction Company (India) Limited
- respondent
Smt. Mydam Nagarani & 8 Others
Coram
Anil Kumar Srivastava
Case details
As recorded by the court registry
All orders in this case
4 orders share this CNR
Similar cases
Judgements on the same questions, provisions and authorities, from every court