Public Works Department v. Y D Builders and Hotels Pvt. Ltd.
Case brief
What is this about?
Section 34 petition challenging an arbitral award was filed with a 646-day delay application. The court held Section 14 Limitation Act excludes only days between institution and termination of a proceeding in a wrong forum; after return of the petition by the Commercial Court, Rohini, no petition remained pending. Delay beyond 120 days not condonable; petition dismissed.