Kleio Solar Power Private Limited v. Vestas Wind Technology India Private Limited
Case brief
What is this about?
Section 9 Arbitration and Conciliation Act 1996 interim relief; suspension of operation and maintenance services under Clause 4.5 O&M Contract; wind turbine generators WTG hybrid solar-wind project; Service and Energy Based Availability Agreement 29.03.2024; Supply Contract 21.03.2023; non-payment of interim fee invoices; wind energy to National Grid of national importance; restore services within three working days; notice of suspension infructuous; O&M Contract restored; right of future suspension preserved; sole arbitrator Justice (Retd.) Vipin Sanghi; DIAC Delhi International Arbitration Centre; DIAC Rules 2018 fees; Section 12 declaration; Section 17 application within two weeks; payment without prejudice; supply agreement arbitration consent; Jasmeet Singh Delhi High Court 18.11.2025.
What did the court decide?
Respondent directed to restore O&M services within three working days; the notice of suspension dated 01.11.2025 declared infructuous and the O&M Contract restored, with parties' rights (including the Respondent's right of future suspension) left open; by consent, Mr. Justice (Retd.) Vipin Sanghi appointed Sole Arbitrator under DIAC aegis with Section 12 declaration, all rights/contentions/arbitrability questions left open, parties to approach the Arbitrator within two days, and any Section 17 application to be adjudicated within two weeks of filing; Supply-Agreement disputes, if raised before the Arbitrator, to be decided by him; Petitioner's payments without prejudice to its rights.