M/S Tewatia Construction Pvt. Ltd. v. Public Works Department Govt of NCT of Delhi
Case brief
What is this about?
Delhi High Court ARB.P. 1932/2025 (18.11.2025, Jasmeet Singh J): Section 11(6) Arbitration and Conciliation Act 1996 petition by Tewatia Construction Pvt Ltd v Public Works Department GNCTD; PWD school classrooms construction contract (additional SPS type classrooms); LOA dated 08.03.2019; Agreement No. 18/EE/Edu.North/PWD/2018-19/3271; Clause 25 GCC arbitration clause; invocation notice dated 21.10.2024; respondent counsel Shiven Varma no objection; Jayesh Kumar SDG (Retd.) CPWD appointed sole arbitrator; DIAC institutional arbitration; Fourth Schedule fees; Section 12 disclosure; arbitrability and preliminary objections left open.
What did the court decide?
Petition under Section 11(6) allowed: Mr. Jayesh Kumar, SDG (Retd.), CPWD appointed as sole arbitrator; arbitration under DIAC aegis; arbitrator's remuneration per Fourth Schedule of the Arbitration & Conciliation Act, 1996; declaration under Section 12 required before entering the reference; all rights and contentions (including arbitrability and preliminary objections) left open; parties to approach the arbitrator within two weeks.