“ In view of the facts pleaded, evidence led and arguments advanced, the Petition partly succeeds. The Respondent is directed to execute the Lease Deed in favour of the Claimant within 6 months from the date of this Award. In case the Respondent is unable to get the Lease Deed executed within the stipulated time frame, with every day of delay, the Respondent shall be liable to pay – interest at the rate of 9 percent per annum to be calculated on the auction consideration of Rs.5.52 crore. The Respondent shall ensure that the Stamp Duty of Rs.33,12,040/-as paid by the Claimant shall be re-utilized. In case of failure of re-utilization of paid Stamp Duty, the Respondent shall refund the paid stamp duty of Rs.33,12,040/to the Claimant along with interest at the rate of 9 percent per annum from date of the Award till date of payment. The Respondent is further directed to provide within 3 months a fresh NOC/EOT, as demanded by the MCD, to the Claimant. The