M/S Rkmt Buildcon Private Limited v. Government of National Capital Territory of Delhi
Case brief
What is this about?
The Delhi High Court allowed the petitioner contractor to refer additional claims to arbitration before a Sole Arbitrator unilaterally appointed by the respondent Government, subject to the parties executing an express agreement waiving the disqualification provisions under Section 12(5) of the A&C Act.
What did the court decide?
The additional claims are referred to arbitration by the Sole Arbitrator appointed by the respondent, subject to the parties entering into an express agreement waiving Section 12(5) of the A&C Act.