DHC allowed an interim application for extending the mandate of an Arbitral Tribunal by six months under Sections 29A(4) and (5) of the Arbitration Act, 1996, citing Supreme Court authority, to enable the Tribunal to pronounce its Award.
What did the court decide?
Extension of the mandate of the Arbitral Tribunal for a period of six months from 10.12.2024.