On a petition for extension of time under Section 29A of the Arbitration and Conciliation Act, 1996, the Court granted an extension of arbitrary proceedings until October 31, 2025, noting the arbitrator acted expeditiously despite delays caused by the parties. Allegations of bias were dismissed as a matter for separate proceedings.
What did the court decide?
Time period for completion of arbitral proceedings and making of arbitral award extended till 31.10.2025.