North East Engineering and Construction (Neecon) v. Brahmaputra Cracker and Polymer Ltd.
Case brief
What is this about?
Allowed two applications under Section 29A(4) of the Arbitration and Conciliation Act, 1996 to extend the mandate of the Arbitral Tribunal for one year until 14.12.2024 to enable the pronouncement of the award.
What did the court decide?
Extended the mandate of the Arbitral Tribunal for one year from 14.12.2024 to 14.12.2025.